Resurfacing works at the University Hospital of North Durham car park are scheduled to begin at 7am on Saturday, 1 February 2025.
The works are expected to take approximately six to seven weekends to complete.
The project will be carried out in four phases, with each phase varying in duration.
Phase 1 details:
-
Scope of Work: Removal of the existing surface binder and base courses, followed by replacement with new materials.
-
Duration: Expected to last three consecutive weekends on the following dates: 1, 2, 8, 9, 15, and 16 February 2025.
-
Opening Times: The affected area will be closed from 11pm Friday and reopen at 6am Monday each week during this phase.
-
Vehicle Removal: All vehicles must be removed from the Phase 1 area outside of the specified opening times.
A temporary traffic management plan will be implemented to minimise disruption to patients, visitors, and staff.
We thank you for your patience and understanding as we work hard to make improvements.